status: [16th March 2011] round one
Fifty percent Renewable Scenarios
ABSTRACT
OzEA now starts considering explicit scenarios for 50% renewable supply in the electricity sector. Early scenarios are rudimentary, and will be refined in an iterative way. For now the focus is on 2003, as dictated by the current solar data. Of particular interest are the demand remainder characteristics.
The task is to site, and assign capacities to, both Concentrating Solar Thermal (CST) plant, and wind farms. Siting is currently limited to those places where we have established wind speed data or solar radiation data respectively.
With the overall NEM demand at ~24 GW average, we seek ~12 GW from solar and wind to obtain around one half of the national electricity requirement from renewables.
INTRODUCTION
By establishing a starting-point 50% renewable scenario we can proceed to examine the consequences and refine the scenario. This in itself is expected to be an ongoing process into the medium term. The reason we need some strong 50% scenarios is so that 30% and 40% scenarios can be built, thus establishing an evolutionary pathway to simulate debate and discussion, and as a basis for further work.
This page is limited to establishing the scenarios (plant and transmission lines), with some associated analysis and collation of results about these scenarios. More detailed work such as establishing flows in transmission lines, and the necessary output from fuelled generators, will occur on other dedicated pages. In the initial stages here the transmission aspects are to be ignored.
The solar data in particular dictates focusing on the years 2003-4-5, and first we work on 2003. Thus there is no demand data for Tasmania (in addition to WA and the NT). The overall demand for the NEM states in 2003 (QLD, NSW, VIC, SA) averages to around 20.6 GW, and while we work below (as per abstract) to set out 12 GW average of renewable supply, this is scaled back to 10.3 when constructing demand remainders.
map (being developed) showing the first 50% renewables scenario
The map figure above shows the renewable supply configuration established for the first 50% renewable scenario, and is followed below by some comments and analysis leading to specifying capacities. Click on the map to get the PDF, and then zoom in and pan around. This will become more important as more detail is included (e.g. transmission lines). Further down again is the demand remainder analysis, including a first gentle prod at the question of storage requirements. I then make some comments to round out the head post, including on the east-west-transmission-link question, before it all turns over to the discussion comments, where developments and evolution mostly happen.
METHODS and DATA
Hypothetical plant is constructed by the application of a wind power curve / CST power curve model to the wind speed data / solar radiation data to obtain output traces for simulated wind farms and simulated CST plants (hourly / half-hourly time series respectively). While these underlying aspects can be developed and refined in various ways, we proceed with what we have for now.
Using the available simulated renewable plant (above), we seek to choose capacity values (sizes) for the individual sites so that the overall combined renewable supply behaves in desired ways. That is we seek to shape the demand remainder profile, and it is critical the reader understand both the 'demand remainder' (being full demand minus renewable supply), and the demand remainder profile (see link in abstract).
In the first instance we simply seek to reduce the maximum value of the demand remainder, and use a simulated annealing approach to do this (as detailed in the comments).
RESULTS
[25th March 2011: The reader can safely skim the next two sections (The CST solar farms and The wind farms), while taking care to follow The Demand Remainder section.]
The CST solar farms
Using the simulated CST farms (in particular this data for 2003) we examine how the available sites might contribute to a national electricity system. This is necessarily crude, and the end point for here and now is simply to select sites and assign capacities.
To start, the simulated CST farms are set at 100 MW capacity by observing that 250 W/m2 intercepted is the usual peak level obtained under the current CST power curve model (with occasional incursions above this when the direct irradiance holds at > ~1100 W/m2). Thus, a collecting area of 400,000 m2 would be required to achieve 100 MW in strong direct sun, and we use this as a starting point for considering all 15 CST data sites. This 100 MW is akin to nameplate capacity for a wind farm - the average output is only a fraction of the peak (i.e. dark half the time, not always strong sun other times).
In order to get a foothold into future analysis, have used a monetary approach to examining the simulated CST farm output. That is, have taken the price data for the NEM states for 2003 (SA, VIC, NSW & QLD), and have used this to calculate the monetary return the CST plants would have made if operating at this time and receiving those prices. This is shown in the table below (with WA receiving SA prices, TAS receiving VIC prices, and the NT receiving QLD prices). Also calculated is the return based on a flat rate of $27 per MWh (the market average for that year, and a low value compared to other years), and using an overall - but time varying - NEM price.
The 'NaN days' column gives the number of days that contained NaN (missing data) runs, these being substantial in some cases, and with missing data requring careful handling. For the Regional and NEM price calculations, have also given the percentage of the overall return that occurs in the most lucrative one percent of the time.
site: NaN CST_avg flat_rate Regional top 1% NEM_price top 1%
days (MW) (mil OzEA$) (mil OzEA$) (mil OzEA$)
---------------------------------------------------------------------------
ADEL 76 17 4.0 4.8 19 3.3 9
MTGAM 54 15 3.4 4.4 19 3.4 20
CRNS 14 18 4.1 3.3 13 3.9 18
ROCKH 25 21 4.8 3.6 10 4.5 17
WAGGA 3 21 4.9 4.6 17 4.5 12
MILD 30 23 5.3 4.8 10 4.8 13
MELB 4 15 3.4 3.2 12 3.2 15
CGRIM 13 13 3.0 2.7 9 2.9 16
BRME 4 28 6.5 8.4 15 8.4 33
LRMTH 59 29 6.7 8.1 14 8.3 29
GRLDN 18 24 5.6 7.8 18 6.3 25
KALG 36 24 5.6 7.4 19 5.9 26
DRWN 32 19 4.3 4.6 33 5.2 32
TENNT 27 29 6.6 5.5 20 6.5 21
ALICE 14 29 6.8 5.4 12 6.5 17
Note the use of 'OzEA$' rather than '2003AU$' - will do this often to signify that the monetary values need to be carefully understood before being lifted into other contexts.
We see that the better sites give up to 29% nameplate as the average, and the poor sites (e.g. Cape Grim in Tasmania, Melbourne) are below 20%. What is also interesting is that there is no clear increase in return at the variable market rate/s compared to the flat rate, excepting the Broome and Learmonth sites, suggesting that perhaps some modest thermal storage as part of the CST might allow better exploitation of the early evening market.
What remains is to select from this limited menu around 6 GW average of Concentrating Solar Thermal electricity generation:
ADEL MTGAM CRNS ROCKH WAGGA MILD MELB CGRIM BRME LRMTH GRLDN KALG DRWN TENNT ALICE
supply (avg) - 17 - 1050 1050 1150 - 13 28 29 24 1200 - 29 1450
nameplate - 100 - 5000 5000 5000 - 100 100 100 100 5000 - 100 5000
Here I have taken five good sites to have large (very large) 5 GW nameplate CST solar farms, and have a further six sites kept in the analysis with 'token' 100 MW plants. In terms of average supply, this gives: 5900 + 145 = 6045 MW, as required. With a further ~6GW from wind, have around one half of the national electricity requirement from renewables.
The wind farms
As detailed here we have 30 simulated wind farms established for 2003. Pricing the electricity from the individual simulated wind farms turns out not to be especially interesting or helpful. As a blunt average ($27 a MWh), a 100 MW nameplate wind farm with 35% capacity factor will earn 8.2 mil OzEA$ for the 2003 year, while pricing the 30 simulated wind farms by the NEM price (weighted average of regional prices), gives returns mostly in the 7-8 million range, with Goulburn Airport (BoM_070330) being the only one to beat the flat rate, coming in at 8.9 million -- and with two SA sites taking up the rear with 6.3 and 6.5 million (BoM_023373 and BoM_023875).
We wish to have a total average of 6 GW wind power, and this can be achieved by simply having each of the 30 wind farms at 570 MW nameplate capacity (as the wind farms have an imposed 35% capacity factor: 30 * 0.35 * 570 = 5985 ~ 6 GW, as reqd).
The Demand Remainder
For the above described 50% renewable scenario, for analysis of the year 2003, with the renewable electricity from wind and CST in equal parts, the following demand remainder profile is calculated:
erratum: the plot should say 25% CST and 25% Wind
(adding to 50% renewable electricity)
Of immediate interest here is where the tails end. The raw demand tops out at 28.5 and the demand remainder for our scenario has toped at 24.1 (a fifteen percent reduction; i.e. a 15% capacity credit for 50% renewables). Ideally this wants to be somewhere ~50%, although what really matters is a more complex calculation of costs for peaking infrastructure. If this can be bought to ~50% without needing to do cartwheels, that will be very encouraging and constitute a significant win in addressing the problems, real and perceived, with high penetration renewables. If, conversely, this empirically calculated capacity credit remains stubbornly low, then it's not the end of the world, but nor is it encouraging.
[Fri 25th March 2011]
There has been some confusion here about the use of "capacity credit".
The antidote is to properly understand what the demand remainder profile represents (see link in Abstract).
Note also that we do not use, nor rely upon, the "capacity credit" for any calculation or conclusion - its use is
an artifice with two specific purposes: (i) to get started on shaping demand remainder profiles via the
parameterisation of the renewable supply, and (ii) to (hopefully) score a rhetorical point in dismantling
the "renewables can't do baseload" [sic] meme.
Storage will likely be the key here, both centralised (as Pumped Storage Hydro, also maybe some boutique hydrogen), and internal to the CST plant. To start we use a centralised view of storage, eventually moving onto the economics of CST-site-storage vs. transmission and networked storage.
Transmission
The transmission lines are not so interesting yet. Can (and will) draw lines on the map connecting the generators to loads, but before much can be said about these it seems necessary to bring in the machinery for (a) defining the flows, and (b) pricing the electricity and thus moving into the economics. These aspects are being worked on, but it all takes time. Sun goes up, sun goes down, arms on the clock go round and around.
(Opening) DISCUSSION
A first concrete scenario, however rudimentary, provides a national renewable supply trace that can be examined and refined. Even before needing to address the transmission requirements, the gross demand remainder profile gives insight and a specific problem to work on. That is, how can the scenario be adjusted in order to shape the demand remainder.
For now we include transmission capability as needed to connect the renewable supply to loads, including a large east-west transmission capability. In time will need to explicitly address the pros and cons (and likelihood, timing, sizing) of any major new transmission infrastructure required by the scenarios.
OzEA now starts including costs into the analysis and modelling work, albeit just around the edges for the moment. One very particular reason is that in optimising system configurations it is ultimately overall cost we want to optimise against. However, please be very careful not to take cost values from these pages to other contexts without a full understanding of what they embody.
Expect the latter part of 2011 will involve detailed modelling of the electricity flows and the temporal requirements from the intermediate and peaking supply infrastructure. This will also involve modelling the market (i.e. the electricity price). This work will of course be developed openly and incrimentally.








Post Comment: